Guide · Building from abroad

How to manage a build in Nigeria from abroad

You can run a Nigerian build from London or Houston if four things are in place: a registered contractor on a written contract, an itemised BOQ, payments released per inspected stage, and reporting you can see for yourself: a live site camera, dated photo reports and regular video walk-rounds.

By Chief Chinedu Edward Makama, MBA, Managing Director · Last verified

Who does what

Roles on a diaspora build
RoleResponsibility
You (the client)Brief, budget, decisions on design and finishes, releasing stage payments.
Design teamArchitectural and structural drawings, approvals.
Contractor / project managerBuilds to the drawings and BOQ, manages trades and materials, reports progress.
InspectorChecks each stage against the drawings before payment is released. Ideally independent of the contractor; at minimum named and qualified.
LawyerLand title, contract review, power of attorney if needed.
Quantity surveyorPrepares or checks the BOQ and values variations.

Building from abroad

Build in Nigeria from anywhere, in six steps

You make the decisions from where you live. We do the work on the ground and show you the proof at every step.

LondonUKNew YorkUS EastTorontoCanadaLagosWAT · UTC+1
  1. Step 1

    Free call

    Tell us your plot, budget and timeline, on video or WhatsApp at a time that suits your time zone.

  2. Step 2

    Land and site check

    Send the documents. We check the plot, access and soil, and work with your lawyer on the title.

  3. Step 3

    Design and approvals

    Approve the design and 3D visuals on video calls. We prepare the drawings and permit application.

  4. Step 4

    BOQ and contract

    Review every line of the open-book BOQ, then sign a contract with stages and inspections built in.

  5. Step 5

    Build, watched live

    Follow the live camera and weekly reports. Pay each stage only after it has been inspected.

  6. Step 6

    Handover

    Receive the keys, as-built drawings, certificates and a 6–12 month defects period.

Calls are booked Monday to Saturday, 09:00–17:00 Lagos time. Lagos has no daylight saving, so the gap to London and North America changes by an hour twice a year.

Pay in stages, never ahead of work

Split the budget into stages (foundation, frame and blockwork, roof, services, finishing) and release each payment only when the previous stage has been inspected. Our cost guide shows what each stage typically costs.

Reporting you can check yourself

Reporting you can check yourself

What you see while we build

Not a relative’s phone photos: dated, regular evidence you can check from anywhere.

W1W2W3W4W5W6W7W8W9W10W11W12
Live site cameraAny time, on your phone
Weekly photo reportEvery week
Stage inspection reportAt every stage gate
Drone or walk-round videoAt key milestones
Your client portalStages, payments, documents
Illustration of a typical 12-week stretch of a build. Inspection dates follow the stages in your programme.

Control changes and costs

When to visit

If you can only travel once or twice, time the visits for setting out and foundation (the building’s position and size are fixed) and before finishing (you choose tiles, fittings and colours in person). Otherwise send an independent professional rather than a relative.

Time zones and communication

Lagos is on West Africa Time (UTC+1, no daylight saving): the same as London in summer and an hour ahead in winter; 5–6 hours ahead of New York and Toronto. Fix a weekly call at a time that suits you, and keep decisions in writing on email or WhatsApp.

Questions people ask

Can I build a house in Nigeria while living abroad?
Yes. Use a registered contractor on a written contract with an itemised BOQ, pay per inspected stage, and follow progress through a live camera, dated reports and video calls.
How often should my contractor report?
Weekly written reports with dated photos, plus inspection reports at every stage and a monthly video walk-round. A live camera lets you check any day.
Do I need to travel to Nigeria during the build?
It helps to visit at setting-out and before finishing, but it isn’t essential if a named, qualified inspector signs off each stage and you see the report.