The short answer
- —2-bedroom (~90 m²): ₦13.5m–₦20m basic · ₦20m–₦29.5m standard.
- —3-bedroom (~130 m²): ₦19.5m–₦28.5m basic · ₦28.5m–₦43m standard · ₦43m–₦58.5m premium.
- —4-bedroom (~170 m²): ₦25.5m–₦37.5m basic · ₦37.5m–₦56m standard · ₦56m–₦76.5m premium.
- —Timeline: usually 6–12 months from approval to handover.
Bungalow costs at a glance
| Bungalow | Basic | Standard | Premium |
|---|---|---|---|
| 2-bedroom bungalow (~90 m²) | ₦13.5m – ₦20m | ₦20m – ₦29.5m | ₦29.5m – ₦40.5m |
| 3-bedroom bungalow (~130 m²) | ₦19.5m – ₦28.5m | ₦28.5m – ₦43m | ₦43m – ₦58.5m |
| 4-bedroom bungalow (~170 m²) | ₦25.5m – ₦37.5m | ₦37.5m – ₦56m | ₦56m – ₦76.5m |
3-bedroom bungalow: cost stage by stage
| Stage | Share | Approx. cost | What it covers |
|---|---|---|---|
| Design, approvals and site preparation | 5–10% | ₦1.5m – ₦4.5m | Drawings, structural design, soil test, building permit, clearing and setting out. |
| Foundation | 10–15% | ₦3m – ₦6.5m | Excavation, blinding, footings or raft, foundation walls, DPC. More on waterlogged or reclaimed land. |
| Frame and blockwork | 20–30% | ₦5.5m – ₦13m | Columns, beams, blockwork, lintels; for a duplex also the first-floor slab and stairs. |
| Roofing | 8–12% | ₦2.5m – ₦5m | Timber or steel trusses, covering (stone-coated or aluminium), fascia and gutters. |
| Services | 10–15% | ₦3m – ₦6.5m | Electrical wiring and fittings, plumbing, septic or soakaway, water storage. |
| Finishing | 30–40% | ₦8.5m – ₦17m | Plaster, screed, tiles, ceilings, paint, doors, windows, sanitary ware, kitchen. |
3-bedroom bungalow, standard finish
Six stages, six checks, six payments
Each bar is a stage’s typical share of the build budget. At the end of every stage the work is inspected and you see the evidence before the next payment is due.
- 1
Design & site prep5–10% · ₦1.4m – ₦4.3m
Drawings, structural design, soil test, building permit, clearing and setting out.
Inspected, then paid
- 2
Foundation10–15% · ₦2.9m – ₦6.5m
Excavation, blinding, footings or raft, foundation walls, DPC. More on waterlogged or reclaimed land.
Inspected, then paid
- 3
Frame & blocks20–30% · ₦5.7m – ₦12.9m
Columns, beams, blockwork, lintels; for a duplex also the first-floor slab and stairs.
Inspected, then paid
- 4
Roof8–12% · ₦2.3m – ₦5.2m
Timber or steel trusses, covering (stone-coated or aluminium), fascia and gutters.
Inspected, then paid
- 5
Services10–15% · ₦2.9m – ₦6.5m
Electrical wiring and fittings, plumbing, septic or soakaway, water storage.
Inspected, then paid
- 6
Finishing30–40% · ₦8.6m – ₦17.2m
Plaster, screed, tiles, ceilings, paint, doors, windows, sanitary ware, kitchen.
Inspected, then paid
4-bedroom bungalow: cost stage by stage
| Stage | Share | Approx. cost | What it covers |
|---|---|---|---|
| Design, approvals and site preparation | 5–10% | ₦2m – ₦5.5m | Drawings, structural design, soil test, building permit, clearing and setting out. |
| Foundation | 10–15% | ₦4m – ₦8.5m | Excavation, blinding, footings or raft, foundation walls, DPC. More on waterlogged or reclaimed land. |
| Frame and blockwork | 20–30% | ₦7.5m – ₦17m | Columns, beams, blockwork, lintels; for a duplex also the first-floor slab and stairs. |
| Roofing | 8–12% | ₦3m – ₦6.5m | Timber or steel trusses, covering (stone-coated or aluminium), fascia and gutters. |
| Services | 10–15% | ₦4m – ₦8.5m | Electrical wiring and fittings, plumbing, septic or soakaway, water storage. |
| Finishing | 30–40% | ₦11.5m – ₦22.5m | Plaster, screed, tiles, ceilings, paint, doors, windows, sanitary ware, kitchen. |
Bungalow or duplex?
| Bungalow | Duplex | |
|---|---|---|
| Cost per m² | Lower: no suspended slab or stairs | Higher: first-floor slab, stairs, heavier frame |
| Land needed | More: everything on one floor | Less: about half the footprint for the same rooms |
| Build time | 6–12 months | 12–24 months |
| Best for | Larger or cheaper plots, ageing parents, adding floors later | Small or expensive plots, privacy between living and sleeping areas |
Current material prices
| Material | Lagos |
|---|---|
| Cement | ₦11,500 – 13,550 /bag |
| Rebar (iron rods) | ₦1,000,000 – 1,200,000 /tonne |
| Granite | ₦25,000 – 30,000 /tonne |
| Sharp sand | ₦12,000 – 15,000 /tonne |
| Aggregate (gravel) | — |
| Ready-mix concrete | — |
Questions people ask
How much does it cost to build a 3-bedroom bungalow in Nigeria?
How much does it cost to build a 4-bedroom bungalow in Nigeria?
How much does it cost to build a 2-bedroom bungalow?
Can I build a bungalow with ₦20 million?
How long does it take to build a bungalow?
Sources and how we checked
- Build With Ease — Cost to build a bungalow vs duplex in Nigeria (2026) (updated May 2026)
- Prioni — Cost of building a house in Nigeria (2026) (June 2026)
- Nigeria Building Cost 2026 estimator (2026)
- Artemis Atelier material price tracker — current cement, rebar, granite, sand and concrete prices