The short answer
- —4-bedroom duplex (~280 m²): ₦42m–₦61.5m basic · ₦61.5m–₦92.5m standard · ₦92.5m–₦126m premium.
- —5-bedroom duplex (~350 m²): ₦52.5m–₦77m basic · ₦77m–₦115.5m standard · ₦115.5m–₦157.5m premium.
- —Finishing is the biggest single stage (30–40%); the first-floor slab makes a duplex’s frame stage dearer than a bungalow’s.
- —Timeline: usually 12–24 months from approval to handover.
Duplex costs at a glance
| Duplex | Basic | Standard | Premium |
|---|---|---|---|
| 4-bedroom duplex (~280 m²) | ₦42m – ₦61.5m | ₦61.5m – ₦92.5m | ₦92.5m – ₦126m |
| 5-bedroom duplex (~350 m²) | ₦52.5m – ₦77m | ₦77m – ₦115.5m | ₦115.5m – ₦157.5m |
4-bedroom duplex: cost stage by stage
| Stage | Share | Approx. cost | What it covers |
|---|---|---|---|
| Design, approvals and site preparation | 5–10% | ₦3m – ₦9.5m | Drawings, structural design, soil test, building permit, clearing and setting out. |
| Foundation | 10–15% | ₦6m – ₦14m | Excavation, blinding, footings or raft, foundation walls, DPC. More on waterlogged or reclaimed land. |
| Frame and blockwork | 20–30% | ₦12.5m – ₦28m | Columns, beams, blockwork, lintels; for a duplex also the first-floor slab and stairs. |
| Roofing | 8–12% | ₦5m – ₦11m | Timber or steel trusses, covering (stone-coated or aluminium), fascia and gutters. |
| Services | 10–15% | ₦6m – ₦14m | Electrical wiring and fittings, plumbing, septic or soakaway, water storage. |
| Finishing | 30–40% | ₦18.5m – ₦37m | Plaster, screed, tiles, ceilings, paint, doors, windows, sanitary ware, kitchen. |
4-bedroom duplex, standard finish
Six stages, six checks, six payments
Each bar is a stage’s typical share of the build budget. At the end of every stage the work is inspected and you see the evidence before the next payment is due.
- 1
Design & site prep5–10% · ₦3.1m – ₦9.3m
Drawings, structural design, soil test, building permit, clearing and setting out.
Inspected, then paid
- 2
Foundation10–15% · ₦6.2m – ₦13.9m
Excavation, blinding, footings or raft, foundation walls, DPC. More on waterlogged or reclaimed land.
Inspected, then paid
- 3
Frame & blocks20–30% · ₦12.3m – ₦27.8m
Columns, beams, blockwork, lintels; for a duplex also the first-floor slab and stairs.
Inspected, then paid
- 4
Roof8–12% · ₦4.9m – ₦11.1m
Timber or steel trusses, covering (stone-coated or aluminium), fascia and gutters.
Inspected, then paid
- 5
Services10–15% · ₦6.2m – ₦13.9m
Electrical wiring and fittings, plumbing, septic or soakaway, water storage.
Inspected, then paid
- 6
Finishing30–40% · ₦18.5m – ₦37m
Plaster, screed, tiles, ceilings, paint, doors, windows, sanitary ware, kitchen.
Inspected, then paid
5-bedroom duplex: cost stage by stage
| Stage | Share | Approx. cost | What it covers |
|---|---|---|---|
| Design, approvals and site preparation | 5–10% | ₦4m – ₦11.5m | Drawings, structural design, soil test, building permit, clearing and setting out. |
| Foundation | 10–15% | ₦7.5m – ₦17.5m | Excavation, blinding, footings or raft, foundation walls, DPC. More on waterlogged or reclaimed land. |
| Frame and blockwork | 20–30% | ₦15.5m – ₦34.5m | Columns, beams, blockwork, lintels; for a duplex also the first-floor slab and stairs. |
| Roofing | 8–12% | ₦6m – ₦14m | Timber or steel trusses, covering (stone-coated or aluminium), fascia and gutters. |
| Services | 10–15% | ₦7.5m – ₦17.5m | Electrical wiring and fittings, plumbing, septic or soakaway, water storage. |
| Finishing | 30–40% | ₦23m – ₦46m | Plaster, screed, tiles, ceilings, paint, doors, windows, sanitary ware, kitchen. |
Why a duplex costs more per m² than a bungalow
- The first-floor slab and staircase. Concrete, rebar and formwork for the suspended floor add a whole extra structural stage.
- Heavier foundations and columns to carry two floors.
- Scaffolding and working at height for the upper floor and roof.
- But a duplex uses less land and roof per bedroom, so on expensive plots it is often the better use of money.
Ways to save without cutting corners
- Keep the plan simple: a rectangular footprint and stacked walls and wet rooms cut concrete, rebar and plumbing.
- Fix the design before you start. Changes during the build are the most expensive changes.
- Buy materials in bulk per stage when prices dip — we track them on our price tracker.
- Spend on structure and waterproofing; upgrade finishes later if you need to.
- Pay per inspected stage, so you never pay for work that has to be redone.
Current material prices
| Material | Lagos |
|---|---|
| Cement | ₦11,500 – 13,550 /bag |
| Rebar (iron rods) | ₦1,000,000 – 1,200,000 /tonne |
| Granite | ₦25,000 – 30,000 /tonne |
| Sharp sand | ₦12,000 – 15,000 /tonne |
| Aggregate (gravel) | — |
| Ready-mix concrete | — |
Questions people ask
How much does it cost to build a 4-bedroom duplex in Nigeria?
How much does it cost to build a 5-bedroom duplex in Nigeria?
How long does it take to build a duplex?
Can I build a duplex in stages as money comes in?
Does the cost include the boys’ quarters (BQ) and fence?
Sources and how we checked
- Build With Ease — Cost to build a bungalow vs duplex in Nigeria (2026) (updated May 2026)
- Prioni — Cost of building a house in Nigeria (2026) (June 2026)
- Nigeria Building Cost 2026 estimator (2026)
- Artemis Atelier material price tracker — current cement, rebar, granite, sand and concrete prices